First technical FAIR facility receives its centerpiece
Tuesday 6 December 2022
Press release, 6th December 2022 "Coldbox" of the cooling system for the superconducting accelerator magnets delivered A large heavy goods transport set off from Aschaffenburg to Darmstadt
on November 30, 2022. Its destination was the international accelerator
facility FAIR (Facility for Antiproton and Ion Research), which is
currently being built at the GSI Helmholtzzentrum für
Schwerionenforschung. Loaded was the so-called “coldbox”, a steel tank
with a length of 18 meters, a height of more than 4.5 meters and a
weight of 85 tons. The coldbox is the heart of the cryogenics facility,
produced and installed by Linde Engineering. It is used to cool and
liquefy helium for the FAIR accelerator. Following the shell
construction and the technical building services, the cryogenics plant
is the first technical facility to be brought into the FAIR buildings. The
huge cooling facility will supply liquid helium to two key FAIR
building blocks, the FAIR ring accelerator SIS100 and also the Super
Fragment Separator (Super-FRS). In the future, ions — charged atoms —
will whiz around the curves of the SIS100 ring accelerator at up to 99%
the speed of light, then collide with samples of materials to produce
nuclear reactions. The Super-FRS is a giant sorting machine for newly
produced, exotic atomic nuclei which can tell us about states in stars
and other stellar events. With these and other large-scale devices,
scientists at FAIR hope to bring the universe into the laboratory. In
order to guide the particles along their paths, strong magnetic fields
are required in both cases, which can only be achieved through the
phenomenon of superconductivity: Extreme cryogenic temperatures can
cause the electrical resistance in some materials to nearly disappear,
allowing high electrical currents to flow in the electromagnets. To
achieve this, the magnets must be cooled to a temperature of four kelvin
(- 269°C). For that purpose, the cryogenic system delivers a maximum
flow rate of over 21,000 liters of liquid helium per hour, for a total
helium storage of nine tons, with a maximum cooling capacity of 14
kilowatts at four kelvin. “The delivery of the coldbox to the FAIR
construction site is a milestone and a sign of the steady progress
being made in the construction of FAIR. The coldbox is the heart of the
cryogenic facility, the first high-tech system to be installed in the
newly constructed FAIR buildings on the construction site. This will
bring us a big step closer to our goal of accelerating particles to
almost the speed of light. Linde Engineering is an important partner in
this process,” says Jörg Blaurock, Technical Managing Director of FAIR
and GSI. “The FAIR cryogenic plant is one of the largest possible
refrigeration plants that can still be built from one unit. For even
higher cooling loads, several plants would have to be used in parallel,”
explains Dr. Holger Kollmus, who as head of the Cryogenics Department
at GSI/FAIR is responsible for the construction of the plant. “A special
feature of the plant is the possibility to change the cooling capacity
dynamically. Comparable plants, which are mainly used for the production
of liquid helium, permanently run at full load. Since the required
cooling capacity for the accelerator fluctuates depending on the
operating condition, the plant is designed to adjust its pressures and
mass flows accordingly to save energy and coolant. Efficient response to
changing loads places high demands on the design and construction of
the unit.” As a contract partner, Linde Engineering is responsible
for the production and installation of the helium cooling facility on
site. Two large buildings are available at FAIR to house the plant
components and now the coldbox. Several large pieces of equipment, such
as compressors, have already been delivered and integrated into the
plant in the past weeks. The coldbox, the largest and central component
of the system, was manufactured by Linde Engineering at its Schalchen
plant. From there, the unit was driven by transporter to Passau, brought
to Aschaffenburg by ship and reloaded onto the final heavy goods
transport to GSI/FAIR. Mechanical completion of the entire plant is
scheduled for mid-2023.
|